MAIDEN DRILLING PROGRAM COMMENCES AT HIGHLY
PROSPECTIVE TAMBOURAH LITHIUM PROJECT, WA
3,800m RC drill program underway to test spodumene-bearing pegmatite dykes
Highlights
•
The initial 3,800m Reverse Circulation (RC) drilling program has commenced at Trek’s
100%-owned Tambourah Lithium Project in the Pilbara region of Western Australia.
•
This maiden drill program has been designed to follow-up the high-grade lithium
spodumene-bearing pegmatite dykes identified at surface in the Eastern Prospect area,
where high-grade rock chip results were returned last year:
o
3.07% Li2O in TKL0045
o
2.69% Li2O in TKL0042
o
2.36% Li2O in TKL0095
o
2.28% Li2O in TKL0044
o
2.11% Li2O in TKL0083
•
The program will also test the high-priority Central Prospect area, where lithiumcaesium-tantalum (LCT) pegmatites and fractionated fertile pegmatites are interpreted
to be located within or close to the lithium zone.
•
Drilling is anticipated to take approximately one month to complete, with laboratory
result turnaround times of approximately 4 weeks.
Trek Metals Limited (ASX: TKM) (“Trek” or “the Company”) is pleased to advise that it has commenced
its maiden drilling program at the 100%-owned Tambourah Lithium Project, located ~70km south-east
of the world-class Pilgangoora lithium deposit in the Pilbara region of Western Australia.
The drilling program will test multiple spodumene-bearing pegmatite dykes identified last year with
high-grade lithium values in surface rock chip samples.
Trek’s CEO Derek Marshall said: “The commencement of our first lithium-focused drill campaign marks
an exciting milestone for the Company. It is the culmination of over a year of field work in delineating
what Trek believes is an exceptional greenfields lithium exploration opportunity at Tambourah.
“We have worked up and de-risked these exciting lithium targets – now it’s now time to let the drill rig
to do the talking!
1
“It’s great to see the rig turning, testing beneath the high-grade rock chips we unearthed last year. The
program has been designed to give us our first real look at the dimensions of the system at depth below
the outcropping pegmatites, while also potentially helping us to vector into new discoveries at depth
and under cover.
Figure 1: Drill rig on site at the Tambourah Lithium Project, targeting areas of high-grade spodumene-bearing lithium
pegmatites in the Eastern Prospect area.
Exploration Program
Trek’s maiden drill program at Tambourah will comprise:
•
19 holes of Reverse Circulation (RC) drilling;
•
each drilled to a depth of ~200m for a total of 3,800m (Figures 2 & 3);
•
providing broad coverage across the project area, with particular focus on the Eastern
Prospect area (Figure 2).
The Eastern Prospect area hosts high-grade outcropping spodumene-bearing pegmatites across
numerous sub-parallel dykes (Figure 2 & refer ASX: TKM 7th November 2022).
2
Figure 2: Planned drill collars locations designed to test rock chip assay results in the Eastern Prospect area which
highlight multiple pegmatite dykes containing high-grade lithium. Note that TKL0042, 46 & 83 were included in a
selected analytical program that confirmed the presence of spodumene (refer ASX: TKM 27th October 2022)
A recent review upgraded the prospectivity of the Central Prospect area (Figure 3) due to the apparent
fractionation trends defining classic LCT pegmatite zonation within soil data (refer ASX: TKM 14th
February 2023). The samples were selected for geochemical analysis due to the abundance of mapped
pegmatites, the anomalous lithium values in stream sediment samples and the fertility ratios – e.g.,
K/Rb in rock chips – in this Central Prospect area (refer ASX: TKM 7th November 2022).
3
Figure 3: Planned drill collar locations across the greater project area, with updated rock chip classification showing the
majority of rocks within the Eastern Prospect area are LCT pegmatites (including the spodumene-bearing pegmatites
discovered late 2022) and, encouragingly, the Central Prospect area is dominated by Fertile Pegmatites, interpreted to
be proximal to lithium-bearing LCT pegmatites.
Trek looks forward to updating the market in due course on the progress of drilling. The duration of
the maiden drilling program is anticipated to be approximately one month, with current assay
turnaround times of approximately 4 weeks. In the event that the exploration program has visible
drilling success Trek is likely to extend the program, depending on drill rig availability.
About the Tambourah Project
The Tambourah Lithium Project is located 70km south-east of Pilbara Minerals’ (ASX: PLS) world-class
Pilgangoora lithium mine site in the Pilbara region of Western Australia (Figure 4). Trek’s extensive
landholding at Tambourah comprises two Exploration Licences (E45/5484 & E45/5839) which are
100%-owned by ACME Pilbara Pty Ltd, a wholly owned subsidiary of Trek Metals Ltd.
The Project encompasses large areas of the Western Shaw Greenstone Belt, predominantly within the
hinge and eastern limb of an anticline folded around the Tambourah Dome. The greenstone rocks
comprise Archean-aged metavolcanic, metasedimentary, and various granitoids with associated
pegmatitic phases. Historic exploration data highlighted the potential for lithium-bearing pegmatite
mineralisation on both of Trek’s tenements (refer ASX: TKM 26th May 2022 for additional information).
4
Figure 4: Location of the Tambourah Lithium Project ~70km SE of world class lithium mines Pilgangoora and Wodgina.
Both stream sediment and rock chip data (Figures 2 & 3) indicate the presence of highly fractionated
Lithium-Caesium-Tantalum (LCT) pegmatites with the potential for lithium mineralisation. Recent rock
chip data has confirmed the presence of high-grade spodumene lithium mineralisation with individual
assays up to 3.07% Li2O (refer ASX: TKM 7th November 2022 for additional information).
5
Authorised by the Board.
ENDS
For further information contact:
INVESTORS:
MEDIA:
Derek Marshall
Nicholas Read
dmarshall@trekmetals.com.au
info@trekmetals.com.au
0419 929 046
DISCLAIMERS AND FORWARD-LOOKING STATEMENTS
This announcement contains forward looking statements. Forward looking statements are often, but not always,
identified A words such as "seek", “target”, "anticipate", “forecast”, "believe", "plan", "estimate", "expect" and
"intend" and statements that an event or result "may", "will", "should", "could" or "might" occur or be achieved
and other similar expressions.
The forward-looking statements in this announcement are based on current expectations, estimates, forecasts
and projections about Trek and the industry in which it operates. They do, however, relate to future matters
and are subject to various inherent risks and uncertainties. Actual events or results may differ materially from
the events or results expressed or implied by any forward-looking statements. The past performance of Trek is
no guarantee of future performance.
None of Trek’s directors, officers, employees, agents or contractors makes any representation or warranty
(either express or implied) as to the accuracy or likelihood of fulfilment of any forward-looking statement, or
any events or results expressed or implied in any forward-looking statement, except to the extent required by
law. You are cautioned not to place undue reliance on any forward-looking statement. The forward-looking
statements in this announcement reflect views held only as at the date of this announcement.
COMPETENT PERSONS STATEMENT
The information in this report relating to Exploration Results is based on information compiled by the Company’s
Chief Executive Officer, Mr Derek Marshall, a competent person, and Member of the Australian Institute of
Geoscientists (AIG). Mr Marshall has sufficient experience relevant to the style of mineralisation and to the type
of activity described to qualify as a competent person as defined in the 2012 Edition of the “Australasian Code
for Reporting of Exploration Results, Mineral Resources and Ore Reserves.” Mr Marshall has disclosed that he
holds Performance Rights in the Company. Mr Marshall consents to the inclusion in this announcement of the
matters based on his information in the form and content in which it appears.
6
JORC Table Section 1: Sampling Techniques and Data:
Criteria
Sampling
techniques
Drilling
techniques
Drill sample
recovery
Logging
Sub-sampling
techniques
and sample
preparation
JORC Code explanation
• Nature and quality of sampling (eg cut
channels, random chips, or specific
specialised industry standard measurement
tools appropriate to the minerals under
investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc).
These examples should not be taken as
limiting the broad meaning of sampling.
• Include reference to measures taken to
ensure sample representivity and the
appropriate calibration of any measurement
tools or systems used.
• Aspects of the determination of mineralisation
that are Material to the Public Report. In cases
where ‘industry standard’ work has been done
this would be relatively simple (eg ‘reverse
circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to
produce a 30 g charge for fire assay’). In other
cases more explanation may be required,
such as where there is coarse gold that has
inherent sampling problems. Unusual
commodities or mineralisation types (eg
submarine nodules) may warrant disclosure of
detailed information.
• Drill type (eg core, reverse circulation, openhole hammer, rotary air blast, auger, Bangka,
sonic, etc) and details (eg core diameter, triple
or standard tube, depth of diamond tails, facesampling bit or other type, whether core is
oriented and if so, by what method, etc).
• Method of recording and assessing core and
chip sample recoveries and results assessed.
• Measures taken to maximise sample recovery
and ensure representative nature of the
samples.
• Whether a relationship exists between sample
recovery and grade and whether sample bias
may have occurred due to preferential
loss/gain of fine/coarse material.
• Whether core and chip samples have been
geologically and geotechnically logged to a
level of detail to support appropriate Mineral
Resource estimation, mining studies and
metallurgical studies.
• Whether logging is qualitative or quantitative
in nature. Core (or costean, channel, etc)
photography.
• The total length and percentage of the
relevant intersections logged.
• If core, whether cut or sawn and whether
quarter, half or all core taken.
• If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet or
dry.
• For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
Commentary
• Rock chip sampling conducted by Trek Metals Limited targeted visual
pegmatite occurrences.
•
Rocks of approximately 1-1.5kg were collected from in-situ material at surface
deemed to be representative by a qualified field geologist, placed in prenumbered calico bags and submitted to Nagrom Laboratory in Kelmscott for
analysis.
•
Location of samples were recorded by handheld GPS.
•
Not applicable, no drilling reported.
•
Not applicable, no drilling reported.
•
Qualitative geological descriptions were recorded by a Trek geologist and
recorded in the database for rock chip samples.
•
Rock chips were collected in field from outcrop sampling.
7
Criteria
Quality of
assay data
and
laboratory
tests
Verification of
sampling and
assaying
Location of
data points
Data spacing
and
distribution
JORC Code explanation
• Quality control procedures adopted for all subsampling stages to maximise representivity of
samples.
• Measures taken to ensure that the sampling is
representative of the in-situ material collected,
including for instance results for field
duplicate/second-half sampling.
• Whether sample sizes are appropriate to the
grain size of the material being sampled.
• The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or
total.
• For geophysical tools, spectrometers,
handheld XRF instruments, etc, the
parameters used in determining the analysis
including instrument make and model, reading
times, calibrations factors applied and their
derivation, etc.
• Nature of quality control procedures
adopted (eg standards, blanks, duplicates,
external laboratory checks) and whether
acceptable levels of accuracy (ie lack of bias)
and precision have been established.
•
The verification of significant intersections by
either independent or alternative company
personnel.
•
The use of twinned holes.
•
Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
•
Discuss any adjustment to assay data.
• Accuracy and quality of surveys used to locate
drill holes (collar and down-hole surveys),
trenches, mine workings and other locations
used in Mineral Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
•
•
•
Orientation of
data in
relation to
geological
structure
•
Sample
security
•
•
Data spacing for reporting of Exploration
Results.
Whether the data spacing and distribution is
sufficient to establish the degree of geological
and grade continuity appropriate for the
Mineral Resource and Ore Reserve estimation
procedure(s) and classifications applied.
Whether sample compositing has been
applied.
Whether the orientation of sampling achieves
unbiased sampling of possible structures and
the extent to which this is known, considering
the deposit type.
If the relationship between the drilling
orientation and the orientation of key
mineralised structures is considered to have
introduced a sampling bias, this should be
assessed and reported if material.
The measures taken to ensure sample
security.
Commentary
•
Rocks collected by Trek were analysed by peroxide fusion digest with ICP
finish (ICP004) at Nagrom in Kelmscott.
•
Nagrom utilized OREAS147 & OREAS999 and duplicate analysis as routine
laboratory QAQC.
•
This method is considered appropriate for lithium exploration.
•
Not applicable, no drilling reported.
•
All company data has been verified and included in the company database.
•
Lithium results in rock chips was converted from elemental Li to Li2O for the
purpose of reporting. The conversion used was Li2O = Li x 2.153.
•
Location of samples collected by Trek were recorded using a handheld
GPS which is considered appropriate at this stage of exploration.
•
Grid projection system is GDA20 MGA Zone 50.
•
Surface RL data is collected using GPS.
•
Rock chip sampling is not regular and follows geological features which is
considered appropriate for this early stage of mineral exploration.
•
No orientation bias is considered to have an effect on the data, however this
at this early stage of exploration the exact influence is unknown.
•
Chain of custody is managed by the Company. Samples are freighted
directly to the laboratory with the appropriate documentation.
8
Criteria
Audits or
reviews
JORC Code explanation
• The results of any audits or reviews of
sampling techniques and data.
Commentary
• No audits or reviews of the sampling techniques or data has been carried
out due to the early stage of exploration, it is considered by the Company
that industry best practice methods have been employed at all stages of
exploration to date.
JORC Table Section 2: Reporting of Exploration Results:
(Criteria listed in the preceding section also apply to this section.)
Criteria
Mineral
tenement and
land tenure
status
JORC Code explanation
• Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint
ventures, partnerships, overriding royalties,
native title interests, historical sites,
wilderness or national park and environmental
settings.
• The security of the tenure held at the time of
reporting along with any known impediments
to obtaining a license to operate in the area.
Commentary
• The Tambourah Project is located 80 km south-west of Marble Bar and
comprises granted licences E45/5484 and E45/5839 held by ACME Pilbara
Pty Ltd (“APP”), a 100% owned subsidiary of Trek Metals Ltd.
•
The Project is located on Palyku Country and intersects two determined
claims WAD23/2019: Palyku and Palyku #2 (WCD2021/003) & WAD23/2019:
Palyku Part A (WCD2019/002) both represented by the Palyku-Jartayi
Aboriginal Corporation (PJAC). APP has an Aboriginal Heritage Agreement
with PJAC for Exploration Licences E45/5839 & E45/5484 and has
undertaken on-country heritage surveys and utilised traditional owner
monitors during ground disturbing activities.
•
E45/5484 has 29% overlap with Class C Reserve R 21802 Pastoral Research
Station.
Exploration
done by other
parties
•
Acknowledgment and appraisal of exploration
by other parties.
•
FMG (2016-2020): Mt Webber (Glacier Valley) Project carried out a stream
sediment sampling and rock chip sampling targeting gold, base metal and
lithium, tin and tantalum mineralisation. Refer WAMEX Final Surrender
Report A124826.
Geology
•
Deposit type, geological setting and style of
mineralisation.
•
Mineralisation identified at Tambourah is interpreted to be Lithium-CaesiumTantalum (LCT) pegmatite & orogenic gold.
•
LCT pegmatites represent the most highly differentiated (enriched in
incompatible elements such as lithium, ceasium, tin, rubidium and tantalum)
and last to crystallize components of certain granitic melts.
•
LCT pegmatites at Tambourah are predominantly hosted in greenstones of
the West Shaw Greenstone Belt, an Archean belt within the Pilbara Craton
of Western Australia.
•
Not applicable, no drilling reported.
Drill hole
Information
•
•
A summary of all information material to the
understanding of the exploration results
including a tabulation of the following
information for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level –
elevation above sea level in metres) of
the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
If the exclusion of this information is justified
on the basis that the information is not
Material and this exclusion does not detract
from the understanding of the report, the
Competent Person should clearly explain why
this is the case.
9
Criteria
Data
aggregation
methods
Relationship
between
mineralisation
widths and
intercept
lengths
Diagrams
Balanced
reporting
Other
substantive
exploration
data
Further work
JORC Code explanation
• In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (eg cutting of high
grades) and cut-off grades are usually
Material and should be stated.
• Where aggregate intercepts incorporate short
lengths of high grade results and longer
lengths of low grade results, the procedure
used for such aggregation should be stated
and some typical examples of such
aggregations should be shown in detail.
• The assumptions used for any reporting of
metal equivalent values should be clearly
stated.
• These relationships are particularly important
in the reporting of Exploration Results.
• If the geometry of the mineralisation with
respect to the drill hole angle is known, its
nature should be reported.
• If it is not known and only the down hole
lengths are reported, there should be a clear
statement to this effect (eg ‘down hole length,
true width not known’).
• Appropriate maps and sections (with scales)
and tabulations of intercepts should be
included for any significant discovery being
reported These should include, but not be
limited to a plan view of drill hole collar
locations and appropriate sectional views.
• Where comprehensive reporting of all
Exploration Results is not practicable,
representative reporting of both low and high
grades and/or widths should be practiced to
avoid misleading reporting of Exploration
Results.
• Other exploration data, if meaningful and
material, should be reported including (but not
limited to): geological observations;
geophysical survey results; geochemical
survey results; bulk samples – size and
method of treatment; metallurgical test results;
bulk density, groundwater, geotechnical and
rock characteristics; potential deleterious or
contaminating substances.
• The nature and scale of planned further work
(eg tests for lateral extensions or depth
extensions or large-scale step-out drilling).
• Diagrams clearly highlighting the areas of
possible extensions, including the main
geological interpretations and future drilling
areas, provided this information is not
commercially sensitive.
Commentary
•
No data aggregation or truncations were performed.
•
No metal equivalents values have been reported.
•
All rock chip locations are displayed in Figures 2 & 3.
•
Pegmatite fertility has been defined utilising a MgLi vs Li plot, with LCT
Pegmatites Mg/Li<1, Fertile Pegmatites Mg/Li<10, Fractionated Granite
Mg/Li<50 and Barren Granite Mg/Li>50.
•
The true width of mineralization is not currently known due to the early-stage
nature of the exploration.
•
See relevant maps in the body of this announcement.
•
All exploration data and results conducted by Trek to date have been reported.
•
Exploration data for the project continues to be reviewed and assessed and
new information will be reported if material.
•
Further work is detailed in the body of the announcement.
•
Soil and rock chip sampling, in conjunction with mapping will be used to further
define drill targets.
•
First pass exploration drilling just commenced is being undertaken by Reverse
Circulation.