Lithium Bearing Pegmatites intersected at Tambourah
Released
Released
Announcement PDF
4 October 2023
LITHIUM-BEARING PEGMATITES INTERSECTED IN MAIDEN
DRILLING AT TAMBOURAH
Assays from recent RC drilling confirm narrow intervals of lithium mineralisation with
grades up to 1.75% Li2O at the Eastern Prospect, with a much broader pegmatite 55m
intercept at the Central Prospect providing a vector for follow-up drilling.
Highlights
•
Maiden first-pass Reverse Circulation (RC) drilling program completed at the 100%owned Tambourah Lithium Project in the Pilbara region of Western Australia.
•
The drilling intersected multiple narrow lithium-bearing pegmatites, with intercepts
including:
o
5m @ 0.69% Li2O from 36m in TARC002, including:
2m @ 1.44% Li2O from 38m
o
3m @ 0.45% Li2O from 147m in TARC008, including:
1m @ 0.84% Li2O from 148m
o
2m @ 0.72% Li2O from 24m in TARC012, including:
1m @ 1.07% Li2O from 25m
•
The drill program was extended from a planned 3,800m program to 4,093m comprising
a total of 20 holes.
•
Encouragingly the only hole targeting a geophysical target intersected a substantial
width of pegmatite (55m down-hole), opening up the large Central Prospect area as a
priority search space for follow-up drilling.
Trek Metals Limited (ASX: TKM) (“Trek” or “the Company”) is pleased to advise that assay results from
its maiden Reverse Circulation drill program at the 100%-owned Tambourah Lithium Project, located
~70km south-east of the world-class Pilgangoora lithium deposit in the Pilbara region of Western
Australia, have confirmed the presence of fertile lithium-bearing pegmatites.
Trek’s CEO Derek Marshall said: “Intersecting significant lithium grades in pegmatite during our
maiden drill program demonstrates the lithium fertility of the Lithium-Caesium-Tantalum pegmatite
system we have identified at Tambourah. The key now is to identify a structural setting that may have
allowed for a significant accumulation of this high-grade material.
“Several holes were added into the program, including one into a geophysical target which has
returned a significant down-hole width of pegmatite, much greater than was observed on the surface.
1
“The success of this hole has provided a method of targeting thicker accumulations of pegmatite in
this fertile greenstone belt. The significant grades returned in this first batch of samples have elevated
the prospectivity of the greater Tambourah region, although we have further work to do refine our
exploration targeting and vector into thicker, high-grade zones of spodumene mineralisation. We look
forward to updating the market on the upcoming exploration plans at the Tambourah Project.”
The maiden drill program at the Tambourah Project was recently completed and consisted of 4,093m
of Reverse Circulation (RC) drilling completed across 20 drill-holes (refer Table 2, Figures 2 & 5 for collar
information and location).
Drill-holes were designed to drill test beneath high-grade spodumene-bearing lithium rock chips in the
Eastern Prospect area and larger pegmatites in the Central Prospect area, where soil and rock chip
sampling indicated that the pegmatites are highly fractionated (refer ASX: TKM 7th November 2022).
Significant intercepts have been calculated for drill hole assays from Trek’s entire maiden drill program
at Tambourah, being holes TARC001 – TARC020 (Table 1, Figures 1 & 2).
Table 1: Significant intercept* table for Tambourah Project maiden drill program (holes TARC001-TARC020)
Hole ID
TARC001
TARC002
TARC002
TARC003
TARC003
TARC004
TARC007
TARC008
TARC009
TARC009
TARC012
TARC012
TARC013
TARC013
From (m)
74
36
including
To (m)
78
41
Interval (m)
4
5
Li₂O (%)
0.172
0.691
38
138
120
124
185
135
147
including
148
230
235
24
including
25
127
119
122
40
139
122
126
187
136
150
2
1
2
2
2
1
3
1.437
0.228
0.226
0.173
0.119
0.149
0.455
149
232
236
26
1
2
1
2
0.837
0.123
0.185
0.717
26
128
120
123
1
1
1
1
1.072
0.114
0.105
0.123
*Significant intercepts calculated by weighted average of consecutive intervals with greater than 0.1% Li 2O.
Including intercepts calculated by weighted average of consecutive intervals with greater than 0.5% Li 2O.
2
The most significant lithium results came from TARC002 (Figures 1 & 2), with an intercept of 5m @
0.69% Li2O from 36m including 2m @ 1.44% Li2O from 38m.
Figure 1: Cross section A-A’ (see Figure 2 for location) showing significant intercepts in holes TARC002 &
TARC003, drilled under high-grade spodumene-bearing rock chip samples.
3
Figure 2: Completed drill-holes in the Eastern Prospect area. Section line A-A’ relates to Figure 1.
4
Encouragingly, a significant down-hole width of pegmatite (55 metres from 119m down-hole,
including 4m of mafic wall rock internal dilution) was intersected in the final hole of the program,
TARC020 (Figures 3 & 4). This hole targeted a demagnetised zone, providing a key targeting method
for proposed future drill-holes at the project.
Figure 3: Plan view showing TARC020 targeting a demagnetised zone, seen in aeromagnetic TMI data.
Figure 4: Drill spoil from TARC020 highlighting the significant down-hole intersection of pegmatite (in white).
5
Figure 5: Completed drill-holes across the greater project area (black diamonds with drill hole ID) over rock
chip classification and regional geology.
About the Tambourah Project
The Tambourah Lithium Project is located 70km south-east of Pilbara Minerals’ (ASX: PLS) world-class
Pilgangoora lithium mine site in the Pilbara region of Western Australia (Figure 6). Trek’s extensive
landholding at Tambourah comprises two Exploration Licences (E45/5484 & E45/5839) which are
100%-owned by ACME Pilbara Pty Ltd, a wholly owned subsidiary of Trek Metals Ltd.
The Project encompasses large areas of the Western Shaw Greenstone Belt, predominantly within the
hinge and eastern limb of an anticline folded around the Tambourah Dome. The greenstone rocks
comprise Archean-aged metavolcanic, metasedimentary, and various granitoids with associated
pegmatitic phases. Historic exploration data highlighted the potential for lithium-bearing pegmatite
mineralisation on both of Trek’s tenements (refer ASX: TKM 26th May 2022 for additional information).
6
Figure 6: Location of the Tambourah Lithium Project ~70km south-east of world class lithium mines
Pilgangoora and Wodgina.
Both stream sediment and rock chip data (Figures 5) indicate the presence of highly fractionated
Lithium-Caesium-Tantalum (LCT) pegmatites with the potential for lithium mineralisation. Rock chip
data has confirmed the presence of high-grade spodumene lithium mineralisation with individual
assays up to 3.07% Li2O (refer ASX: TKM 7th November 2022 for additional information).
A review upgraded the prospectivity of the Central Prospect area due to the apparent fractionation
trends defining classic LCT pegmatite zonation within soil data (refer ASX: TKM 14th February 2023).
The samples were selected for geochemical analysis due to the abundance of mapped pegmatites, the
anomalous lithium values in stream sediment samples and the fertility ratios – e.g., K/Rb in rock chips
– in this Central Prospect area (refer ASX: TKM 7th November 2022).
7
Table 2: Reverse Circulation (RC) Drill Collar Details
Hole ID
Easting
Northing
RL
Depth
Azi
Dip
Assays
TARC001
TARC002
TARC003
TARC004
TARC005
TARC006
TARC007
TARC008
TARC009
TARC010
TARC011
TARC012
TARC013
TARC014
TARC015
TARC016
TARC017
TARC018
TARC019
TARC020
726,433
725,979
726,026
725,829
725,995
726,181
726,114
726,329
725,936
726,254
726,038
725,977
726,018
725,840
725,908
725,256
724,136
722,963
721,926
723,652
7,600,688
7,601,249
7,601,252
7,601,559
7,601,529
7,601,542
7,601,008
7,600,991
7,601,000
7,601,243
7,601,255
7,601,251
7,601,256
7,601,813
7,601,975
7,602,820
7,603,379
7,603,760
7,603,699
7,603,689
343
342
345
344
338
341
349
343
345
345
339
342
339
336
336
346
353
342
338
344
200
200
226
264
202
196
202
200
250
196
202
142
140
196
274
196
196
214
197
200
269.64
280.57
273.86
269.84
262.62
265.04
266.49
268.73
234.21
78.77
86.86
257.20
233.16
272.91
270.70
236.60
283.88
273.51
275.54
299.05
-54.87
-60.13
-60.94
-59.41
-55.93
-54.32
-54.53
-53.87
-53.92
-55.45
-55.41
-56.14
-55.34
-55.13
-54.67
-54.19
-55.73
-55.30
-56.24
-55.32
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Projection MGA 2020 Z50 EPSG:7850
Authorised by the Board.
ENDS
For further information contact:
INVESTORS:
MEDIA:
Derek Marshall
Nicholas Read
dmarshall@trekmetals.com.au
info@trekmetals.com.au
0419 929 046
DISCLAIMERS AND FORWARD-LOOKING STATEMENTS
This announcement contains forward looking statements. Forward looking statements are often, but not always,
identified A words such as "seek", “target”, "anticipate", “forecast”, "believe", "plan", "estimate", "expect" and
"intend" and statements that an event or result "may", "will", "should", "could" or "might" occur or be achieved
and other similar expressions.
8
The forward-looking statements in this announcement are based on current expectations, estimates, forecasts
and projections about Trek and the industry in which it operates. They do, however, relate to future matters
and are subject to various inherent risks and uncertainties. Actual events or results may differ materially from
the events or results expressed or implied by any forward-looking statements. The past performance of Trek is
no guarantee of future performance.
None of Trek’s directors, officers, employees, agents or contractors makes any representation or warranty
(either express or implied) as to the accuracy or likelihood of fulfilment of any forward-looking statement, or
any events or results expressed or implied in any forward-looking statement, except to the extent required by
law. You are cautioned not to place undue reliance on any forward-looking statement. The forward-looking
statements in this announcement reflect views held only as at the date of this announcement.
COMPETENT PERSONS STATEMENT
The information in this report relating to Exploration Results is based on information compiled by the Company’s
Chief Executive Officer, Mr Derek Marshall, a competent person, and Member of the Australian Institute of
Geoscientists (AIG). Mr Marshall has sufficient experience relevant to the style of mineralisation and to the type
of activity described to qualify as a competent person as defined in the 2012 Edition of the “Australasian Code
for Reporting of Exploration Results, Mineral Resources and Ore Reserves.” Mr Marshall has disclosed that he
holds or controls Shares and Performance Rights in the Company. Mr Marshall consents to the inclusion in this
announcement of the matters based on his information in the form and content in which it appears.
9
JORC Table Section 1: Sampling Techniques and Data:
Criteria
Sampling
techniques
Drilling
techniques
Drill sample
recovery
JORC Code explanation
• Nature and quality of sampling (eg cut
channels, random chips, or specific
specialised industry standard measurement
tools appropriate to the minerals under
investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc).
These examples should not be taken as
limiting the broad meaning of sampling.
• Include reference to measures taken to
ensure sample representivity and the
appropriate calibration of any measurement
tools or systems used.
• Aspects of the determination of mineralisation
that are Material to the Public Report. In cases
where ‘industry standard’ work has been done
this would be relatively simple (eg ‘reverse
circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to
produce a 30 g charge for fire assay’). In other
cases more explanation may be required,
such as where there is coarse gold that has
inherent sampling problems. Unusual
commodities or mineralisation types (eg
submarine nodules) may warrant disclosure of
detailed information.
• Drill type (eg core, reverse circulation, openhole hammer, rotary air blast, auger, Bangka,
sonic, etc) and details (eg core diameter, triple
or standard tube, depth of diamond tails, facesampling bit or other type, whether core is
oriented and if so, by what method, etc).
Commentary
• Drill sampling is conducted by Trek Metals Limited appointed technical
personnel rig side.
•
•
•
Logging
•
•
•
Sub-sampling
techniques
and sample
preparation
•
•
•
Method of recording and assessing core and
chip sample recoveries and results assessed.
Measures taken to maximise sample recovery
and ensure representative nature of the
samples.
Whether a relationship exists between sample
recovery and grade and whether sample bias
may have occurred due to preferential
loss/gain of fine/coarse material.
Whether core and chip samples have been
geologically and geotechnically logged to a
level of detail to support appropriate Mineral
Resource estimation, mining studies and
metallurgical studies.
Whether logging is qualitative or quantitative
in nature. Core (or costean, channel, etc)
photography.
The total length and percentage of the
relevant intersections logged.
If core, whether cut or sawn and whether
quarter, half or all core taken.
If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet or
dry.
For all sample types, the nature, quality and
•
The location of drill holes was located by handheld GPS.
•
RC drilling was sampled on either 1m splits generated by a rig mounted
cyclone and cone splitter or 4m composite samples were collected by spear
sampling green bags as per standard industry practice.
•
Selected intervals of 1m samples within target zones and a selected 4m
composite sample outside of target zones were selected by a qualified field
geologist and submitted to Nagrom Laboratory in Kelmscott for analysis.
•
Early-stage exploration drilling at the Tambourah Project has been
undertaken utilizing a track-mounted reverse circulation (RC) drill rig
operated by Strike Drilling.
•
Reverse circulation drilling used a face sampling bit.
•
Reverse circulation drilling recoveries were good, with any issues noted by
supervising geologist and recorded in the database. There was no observed
relationship between sample recovery and grade.
•
Geological logging descriptions are recorded by a Trek geologist rig side for
every metre of RC drill spoil and validated and recorded in the database.
•
The preparation of the RC samples follows industry practice with a ~3kg
sample retained or dispatched for laboratory assay.
•
Field QA/QC was undertaken with duplicates, standards and blanks inserted
in samples submitted to the laboratory. Additional laboratory QA/QC was
10
Criteria
Quality of
assay data
and
laboratory
tests
Verification of
sampling and
assaying
Location of
data points
Data spacing
and
distribution
JORC Code explanation
appropriateness of the sample preparation
technique.
• Quality control procedures adopted for all subsampling stages to maximise representivity of
samples.
• Measures taken to ensure that the sampling is
representative of the in-situ material collected,
including for instance results for field
duplicate/second-half sampling.
• Whether sample sizes are appropriate to the
grain size of the material being sampled.
• The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or
total.
• For geophysical tools, spectrometers,
handheld XRF instruments, etc, the
parameters used in determining the analysis
including instrument make and model, reading
times, calibrations factors applied and their
derivation, etc.
• Nature of quality control procedures
adopted (eg standards, blanks, duplicates,
external laboratory checks) and whether
acceptable levels of accuracy (ie lack of bias)
and precision have been established.
•
The verification of significant intersections by
either independent or alternative company
personnel.
•
The use of twinned holes.
•
Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
•
Discuss any adjustment to assay data.
• Accuracy and quality of surveys used to locate
drill holes (collar and down-hole surveys),
trenches, mine workings and other locations
used in Mineral Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
Commentary
completed on laboratory samples.
•
•
•
Orientation of
data in
relation to
geological
structure
•
•
Data spacing for reporting of Exploration
Results.
Whether the data spacing and distribution is
sufficient to establish the degree of geological
and grade continuity appropriate for the
Mineral Resource and Ore Reserve estimation
procedure(s) and classifications applied.
Whether sample compositing has been
applied.
Whether the orientation of sampling achieves
unbiased sampling of possible structures and
the extent to which this is known, considering
the deposit type.
If the relationship between the drilling
orientation and the orientation of key
mineralised structures is considered to have
introduced a sampling bias, this should be
assessed and reported if material.
•
Sample sizes are considered appropriate for the material and analysis
method.
•
Samples were analyzed by peroxide fusion digest with ICP finish (ICP004)
at Nagrom in Kelmscott. These techniques are considered full digest and
appropriate for the elements of interest.
•
Certified Reference Material (standards), blanks and field duplicate samples
were inserted into the sample sequence on a regular basis and performed
within acceptable tolerances.
•
Significant intersections have been reviewed by several alternative company
personnel.
•
All company data has been verified and included in the company database.
•
Lithium results have been converted from elemental Li to Li2O for the purpose
of reporting. The conversion used was Li2O = Li x 2.153.
•
Location of samples & holes were recorded using a handheld GPS which is
considered appropriate at this stage of exploration.
•
Grid projection system is GDA20 MGA Zone 50.
•
Surface RL data is collected using GPS.
•
Drilling and sampling targeted LCT pegmatite lithium mineralisation and is
considered appropriate for this early stage of mineral exploration.
•
No orientation bias is considered to have an effect on the data, however this
at this early stage of exploration the exact influence is unknown.
11
Criteria
Sample
security
JORC Code explanation
• The measures taken to ensure sample
security.
Commentary
• Chain of custody is managed by the Company. Samples are freighted
directly to the laboratory with the appropriate documentation.
Audits or
reviews
•
•
The results of any audits or reviews of
sampling techniques and data.
No audits or reviews of the sampling techniques or data has been carried
out due to the early stage of exploration, it is considered by the Company
that industry best practice methods have been employed at all stages of
exploration to date.
JORC Table Section 2: Reporting of Exploration Results:
(Criteria listed in the preceding section also apply to this section.)
Criteria
Mineral
tenement and
land tenure
status
JORC Code explanation
• Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint
ventures, partnerships, overriding royalties,
native title interests, historical sites,
wilderness or national park and environmental
settings.
• The security of the tenure held at the time of
reporting along with any known impediments
to obtaining a license to operate in the area.
Commentary
• The Tambourah Project is located 80 km south-west of Marble Bar and
comprises granted licences E45/5484 and E45/5839 held by ACME Pilbara
Pty Ltd (“APP”), a 100% owned subsidiary of Trek Metals Ltd.
•
The Project is located on Palyku Country and intersects two determined
claims WAD23/2019: Palyku and Palyku #2 (WCD2021/003) & WAD23/2019:
Palyku Part A (WCD2019/002) both represented by the Palyku-Jartayi
Aboriginal Corporation (PJAC). APP has an Aboriginal Heritage Agreement
with PJAC for Exploration Licences E45/5839 & E45/5484 and has
undertaken on-country heritage surveys and utilised traditional owner
monitors during ground disturbing activities.
•
E45/5484 has 29% overlap with Class C Reserve R 21802 Pastoral Research
Station.
Exploration
done by other
parties
•
Acknowledgment and appraisal of exploration
by other parties.
•
FMG (2016-2020): Mt Webber (Glacier Valley) Project carried out a stream
sediment sampling and rock chip sampling targeting gold, base metal and
lithium, tin and tantalum mineralisation. Refer WAMEX Final Surrender
Report A124826.
Geology
•
Deposit type, geological setting and style of
mineralisation.
•
Mineralisation identified at Tambourah is interpreted to be Lithium-CaesiumTantalum (LCT) pegmatite & orogenic gold.
•
LCT pegmatites represent the most highly differentiated (enriched in
incompatible elements such as lithium, caesium, tin, rubidium and tantalum)
and last to crystallize components of certain granitic melts.
•
LCT pegmatites at Tambourah are predominantly hosted in greenstones of
the West Shaw Greenstone Belt, an Archean belt within the Pilbara Craton
of Western Australia.
•
Data provided within body of the announcement, refer Tables 1 & 2.
Drill hole
Information
•
•
A summary of all information material to the
understanding of the exploration results
including a tabulation of the following
information for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level –
elevation above sea level in metres) of
the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
If the exclusion of this information is justified
on the basis that the information is not
Material and this exclusion does not detract
12
Criteria
Data
aggregation
methods
Relationship
between
mineralisation
widths and
intercept
lengths
Diagrams
Balanced
reporting
Other
substantive
exploration
data
Further work
JORC Code explanation
from the understanding of the report, the
Competent Person should clearly explain why
this is the case.
• In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (eg cutting of high
grades) and cut-off grades are usually
Material and should be stated.
• Where aggregate intercepts incorporate short
lengths of high grade results and longer
lengths of low grade results, the procedure
used for such aggregation should be stated
and some typical examples of such
aggregations should be shown in detail.
• The assumptions used for any reporting of
metal equivalent values should be clearly
stated.
• These relationships are particularly important
in the reporting of Exploration Results.
• If the geometry of the mineralisation with
respect to the drill hole angle is known, its
nature should be reported.
• If it is not known and only the down hole
lengths are reported, there should be a clear
statement to this effect (eg ‘down hole length,
true width not known’).
• Appropriate maps and sections (with scales)
and tabulations of intercepts should be
included for any significant discovery being
reported These should include, but not be
limited to a plan view of drill hole collar
locations and appropriate sectional views.
• Where comprehensive reporting of all
Exploration Results is not practicable,
representative reporting of both low and high
grades and/or widths should be practiced to
avoid misleading reporting of Exploration
Results.
• Other exploration data, if meaningful and
material, should be reported including (but not
limited to): geological observations;
geophysical survey results; geochemical
survey results; bulk samples – size and
method of treatment; metallurgical test results;
bulk density, groundwater, geotechnical and
rock characteristics; potential deleterious or
contaminating substances.
• The nature and scale of planned further work
(eg tests for lateral extensions or depth
extensions or large-scale step-out drilling).
• Diagrams clearly highlighting the areas of
possible extensions, including the main
geological interpretations and future drilling
areas, provided this information is not
commercially sensitive.
Commentary
•
Significant intercepts were calculated by weighted average of consecutive
intervals with greater than 0.1% Li2O. Including intercepts were calculated by
weighted average of consecutive intervals with greater than 0.5% Li2O.
•
No metal equivalents values have been reported.
•
All rock chip & drill hole locations are displayed in Figure 5.
•
Pegmatite fertility has been defined utilising a Mg/Li vs Li plot, with LCT
Pegmatites Mg/Li<1, Fertile Pegmatites Mg/Li<10, Fractionated Granite
Mg/Li<50 and Barren Granite Mg/Li>50.
•
The true width of mineralization is not currently known due to the early-stage
nature of the exploration.
•
See relevant maps in the body of this announcement.
•
All exploration data and results conducted by Trek to date have been reported.
•
Exploration data for the project continues to be reviewed and assessed and
new information will be reported if material.
•
Soil and rock chip sampling, in conjunction with mapping will be used to further
define drill targets.
•
First pass exploration drilling was undertaken by Reverse Circulation.
Information from all the holes in the maiden program will be assessed prior to
determining further work.
13